JANUARY
2021
GROUND BREAKING CEREMONY
18th Jan 2021
MARCH
2021
MORE DETAILS
Excavation Levels : 70% Completed
Lean : 50% Completed
JUNE
2021
MORE DETAILS
Excavation Levels : 100% Completed
Lean : 100% Completed
Underground Watertank : 50% Completed
JULY
2021
MORE DETAILS
Excavation Levels : 100% Completed
Lean : 100% Completed
Underground Watertank : 80% Completed
Ready for Rafting
AUGUST
2021
MORE DETAILS
Excavation Levels : 100% Completed
Lean : 100% Completed
Underground Watertank : 80% Completed
Rafting : 15% Completed
NOVEMBER
2021
MORE DETAILS
Lean : 100% Completed
Steel Binding: 30% Completed
Rafting : 25% Completed
MARCH
2022
MORE DETAILS
First Floor Slab : 90% Completed
Ground Floor Slab : 100% Completed
Steel Binding: 100% Completed
Underground Parking : 100% Completed
JUNE
2022
MORE DETAILS
Third Floor Slab: 70% Completed
First Floor Slab : 100% Completed
Second Floor Slab : 100% Completed
JULY
2022
MORE DETAILS
Fifth Floor Column / Beam : 60% Completed
Fourth Floor Slab : 50% Completed
Third Floor Slab: 100% Completed
AUGUST
2022
MORE DETAILS
Fourth Floor Slab : 100% Completed
Sixth Floor Column / Beam : 35% Completed
Fifth Floor Slab : 100% Completed
OCTOBER
2022
MORE DETAILS
Sixth Floor Slab : 100% Completed
Seventh Floor Column / Beam : 75% Completed
Seventh Floor Slab : 0% Completed
DECEMBER
2022
MORE DETAILS
Eight Floor Steel Work : 15% Completed
Seventh Floor Column / Beam : 100% Completed
Seventh Floor Slab : 70% Completed
FEBRUARY
2023
MORE DETAILS
Eight Floor Steel Work : 15% Completed
Seventh Floor Slab : 70% Completed
Seventh Floor Column / Beam : 100% Completed
MAY
2023
MORE DETAILS
Eight Floor Steel Work : 55% Completed
Seventh Floor : 100% Completed
Seventh Floor Column / Beam : 100% Completed
JUNE
2023
MORE DETAILS
Ninth Floor Steel Work : 55% Completed
7th & 8th Floor : 100% Completed
Ninth Floor Column / Beam : 100% Completed
AUGUST
2023
MORE DETAILS
Ninth Floor : 80% Completed
9th Floor Steel Work : 70% Completed
SEPTEMBER
2023
MORE DETAILS
Ninth Floor : 80% Completed
Ninth Floor Steel Work : 70% Completed
DECEMBER
2023
MORE DETAILS
Tenth Floor : 80% Completed
Ninth Floor Steel Work : 100% Completed
FEBRUARY
2024
MORE DETAILS
100% Grey Structure Complete
APRIL
2024
MORE DETAILS
Interior Work Starting
100% Grey Structure Complete